On this page you can continue to view all our project documents. This includes the documents we published for statutory consultation: our 2024 Project Background Document, Preliminary Environmental Information Report (PEIR) and Non-technical Summary of the PEIR (NTS of the PEIR), as well as our 2024 Design Development Report and 2024 Strategic Options Backcheck and Review which provides an overview of the appraisal approach we have used to date to consider strategic options for Norwich to Tilbury.
Further information can be found on our Information for Landowners page.
If you feel your land may be affected by these proposals, please contact the Norwich to Tilbury Land Team at Fisher German by emailing [email protected] or by calling 0808 175 331.
Project Background Document 2024 | Provides an overview of the project, detailing our proposals and how we are consulting. |
Strategic Options Backcheck and Review 2024 | This summarises the method we’ve been using to evaluate our strategic choices. We regularly review and backcheck these methods as we continue to assess and make decisions about our strategic options. |
Maps of our proposals 2024 | Showing the proposed route of our project. |
Design Development Report 2024 | An in-depth technical document detailing the work we have undertaken to date, focusing on the work since previous consultations. |
2023 Non-statutory consultation Feedback Report | Summarises the feedback we received during the 2023 consultation and how it has been considered. |
Community Newsletter April 2024 | An update on the progress of the project. |
Consultation Feedback Form 2024 | To gather consultation comments and feedback. |
Preliminary Environmental Information report non-technical summary | This document is the Non-Technical Summary of the Preliminary Environmental Information Report (PEIR). The PEIR provides the preliminary findings of the Environmental Impact Assessment (EIA) process. |
Preliminary Environmental Information report | This document presents the preliminary findings of the Environmental Impact Assessment (EIA) process for the Norwich – Tilbury project. |
Statement of community consultation | Sets out our proposed approach to consultation for the Norwich – Tilbury project. |
We've produced an updated interactive map to support our 2024 public consultation to make it easier to identify where you are in relation to our proposals.
View the interactive map of our proposals
Using this interactive map, you can:
View our preferred draft alignment detailing our proposed new 400 kV overhead line between the existing Norwich Main substation in Norfolk to the existing substation at Bramford, and from Bramford to the existing Tilbury substation in Essex.
As our proposals relate to the reinforcement of the 400 kV network in East Anglia, this map only illustrates the existing 275 kV and 400kV network along with related substations.
As part of our statutory consultation, we ran a series of webinars to provide more information about our proposals. You can watch these by clicking 'Watch here' below.
Topic | Recording link |
Project Overview One
|
|
Section A and B South Norfolk and Mid Suffolk
|
|
Section C and D Babergh, Tendring and Colchester
|
|
Section E and F – Braintree and Chelmsford
|
|
Section G and H Basildon, Brentwood and Thurrock
|
|
Project Overview Two
|
|