Construction has now begun, with new infrastructure expected to be operational in 2027 and final works and reinstatement anticipated to be complete by the end of 2028.
Construction work will be phased across the different areas which form Yorkshire GREEN. You can find out more about the work happening in different areas by looking at our interactive map.
Morrison Energy Services (MES) has been selected to deliver the new overhead line and existing overhead line refurbishment; Murphy Power Networks (Murphy) will deliver two new substations in Overton and Monk Fryston; and Hyosung and Hyundai will supply transformers to the substations and cable sealing end compounds (a component that joins underground cables with overhead lines).
We are working very closely with our contractors to communicate the work they are undertaking.
Preparatory works for Yorkshire GREEN, which will enable us to begin the main works in early 2025, have now started.
Over the next few weeks there will be some road closures and other traffic management in place to allow us to carry out some of these works.
Some of the preparatory works we need to undertake include:
To allow us to do this work safely, there will be some traffic management and road closures in place over the next few weeks.
You can view the exact locations of the traffic management and road closures in place on our interactive map.
Rawfield Lane, between Monk Fryston and Fairburn – from 1 November until 20 December
The lane closure on Rawfield Lane was originally due to be in place for three weeks. However, in order to complete our preparatory works safely and efficiently, there will need to be an extension of the current lane closure and temporary traffic lights for a further four weeks.
The lane closure, which is between the junction with the A63 and the entrance to Monk Fryston Substation will be in place between 7am – 6pm Monday to Friday. The lane closure was previously in place 24/7.
Temporary traffic lights will remain in place to maintain two-way traffic flow.
Outside of these hours, the lane closure will be removed and the road will be open as normal. We will also open the road as normal if the closure is not needed on a particular day.
Common Croft Lane and Lords Lane, Nether Poppleton – from 1 November for approximately four weeks
From Friday 1 November, Common Croft Lane/Lords Lane will be closed to vehicles, pedestrians and cyclists at the junction of the two roads.
Traffic management measures will extend approximately 20 metres each side of the junction on Common Croft Lane, and 20 metres into Lords Lane.
The closure will be in place between 7am and 7pm Monday to Friday and 8am and 5pm Saturday and Sunday. Outside of these hours the closure will be removed and the road will be open as usual. We will also open the road if the closure is not needed on a particular day.
Once the closure is in place, a staffed gate will be in place at each end of the closure to coordinate access. General traffic that needs to access Lords Lane will be let through by the staff at the gates.
Emergency vehicles will be permitted access immediately and the road will be cleared for them should they need access.
General traffic wishing to access Common Croft Lane between the junctions of Ouse Moor Lane and West Field Lane will be diverted through Upper Poppleton via West Field Lane, Hodgson Lane, and Main Street. Diversion signage will be in place to direct general traffic around the closure.
A659, Tadcaster – from 4 November for approximately four weeks
The lane closure on the A659 in Tadcaster was originally due to be in place for two weeks. However, in order to carry out further preparatory works safely and efficiently, there will need to be an extension of the current lane closure and temporary traffic lights on the A659 for a further two weeks
The lane closure, which is close to the junction with Garnet Lane, will be in place between 7am and 7pm every day. The closure had previously been in 24 hours a day.
Temporary traffic lights will remain in place to maintain two-way traffic flow.
Outside of these hours, the lane closure will be removed and the road will be open as normal. We will also open the road as normal if the closure is not needed on a particular day.
You may also notice some additional traffic in the area during the closure while our delivery vehicles bring materials to the site.
If you have a question, you can contact us in the following ways:
Email us: [email protected]
Call our Freephone number: 0800 029 4359
Write to us: FREEPOST Yorkshire GREEN (please note that you do not need a stamp)
What's energy resilience got to do with movie marathons? Find out how – and why – we’re connecting more clean energy to power the things you love.
Find out more