Through our business planning process, including submission to Ofgem and the negotiation of the RIIO-T2 deal, we had value for money at the heart of it all. We want to deliver a clean, fair and affordable electricity network for all.
The Cost & Volume tables show forecast expenditure of £7.6bn against Final Determination Allowances of £5.7bn – a difference of £1.9bn. Since Final Determination, there have been updates to allowances to reflect our latest view of movements including re-openers submitted, the operation of uncertainty mechanisms and anticipated end of price control adjustments via Price Control Deliverable (PCD) mechanisms. These updates add a further £2.1bn of allowances over the price control period, bringing forecast expenditure £0.2bn less than ‘adjusted’ allowances for the 5-year price control period. The adjustments to allowances by investment area are summarised in the table below:
This is our Regulatory Financial Performance Reporting (RFPR) submission to Ofgem. RFPR contains our financial performance for 2023/24 under the RIIO framework. RFPR enables Ofgem to administer the licence conditions that relate to the price control. This includes monitoring the performance of licensees against Final Determinations, monitoring compliance with price control obligations and reviewing performance between price controls.
Download the 2023/2024 RFPR narrative
Download the 2023/2024 RFPR pack
Archive
Download the 2022/2023 RFPR narrative
Download the 2022/2023 RFPR pack
The following graphic shows the five-year forecast and demonstrates how the price control mechanisms operate to adjust allowances from Final Determinations as requirements change. The graphic also demonstrates the corresponding impact on the overall difference between spend and allowance. NB Please remember that this waterfall excludes spend and agreed funding for ASTI projects.
The overall performance that will be reported in the Regulatory Financial Performance Report will show forecast costs as £1.2bn below allowances (a reduction in underspend compared to the RRP23 view which reported forecast costs to be £1.3bn below allowances). The two reports have a different scope when reporting performance but are based on the same underlying data. The table below outlines the additional elements which are included in RFPR to drive the £1.2bn difference in reported performance to RRP:
There are three categories of adjustments embedded into this position which are explained further below:
Adjustments to reflect timing of spend (‘Phasing of allowances’ and ‘Edge Effects’ in the table above) of £0.8bn
Our ongoing efficiency ambition not embedded at project level of £0.1bn
Other adjustments totalling £0.1bn:
When considering our performance against allowances, we have adjusted the phasing of allowances to match the phasing of output delivery. This is in line with the reversal of enduring value adjustments we made during the RIIO-T1 period with allowances adjusted from the RIIO-T1 period falling into two categories:
Allowances relating to Load-Related projects initiated in RIIO-T1 but completing in the first two years of RIIO-T2 (known as RIIO-T1+2) have been re-profiled for financial reporting purposes to recognise the performance when the output is delivered. This has resulted in an additional £331m of allowance being recognised in the RIIO-T2 period.
This refers to the impact on performance of projects crossing price control periods and shows an apparent over or under spend in one price control period which is offset in the other price control period.
The impact of edge effects was exacerbated in 2022/23 due to the challenges imposed by Covid-19 in the RIIO-T1 period, which delayed some interventions into RIIO-T2. We plan to undertake these replacements during the RIIO-T2 period in addition to delivering the commitments made as part of the RIIO-T2 contract. Financial reporting has re-profiled allowances to reflect this with additional allowances of £0.5bn being reported in the RIIO-T2 period.
Load-Related 5-year view
The Load-Related plan, that is the work to connect customers to the network and make wider network reinforcements, is forecast to deliver the outputs required to meet customer needs for £2.02bn of direct capital expenditure, £418m less than adjusted allowances of £2.44bn. The adjusted allowance position represents an increase of £986m from Final Determinations, driven by:
In the Load-Related portfolio, we have analysed the differences between spend and allowance in order to categorise it as either:
Based on the above methodology, the £407m difference between cost and allowances has been allocated in the following manner (where a positive number is an underspend).
The forecast expenditure for the whole of RIIO-T2 is £7.5bn against Final Determination Allowances of £5.4bn – a difference of £2.1bn. Since Final Determinations, there have been updates to allowances to reflect changes in the Load-Related plan, re-openers submitted and adjustments for investment no longer required, as well as anticipated adjustments which will be enacted at the end of the price control through the relevant mechanisms.
To understand our underlying performance, these updates have been included, adding a further £1.9bn of allowances over the price control period. This results in a reported difference between spend and allowance of £0.1bn for the RIIO-T2 period.
In 2023/24, direct capital expenditure on the Load-Related portfolio was £351m which is £175m less than adjusted allowances of £526m. In addition to the performance factors over the 5-year period, for 2023/24 there is an additional factor for volume-driven (uncertainty mechanism) projects which is the result of misalignment between the generic phasing of allowances compared to a project-specific view of spend across the RIIO-T2 period. This affects some projects with shorter or longer lead times than the assumed 4-year period allowances are profiled over. Based on our plan, we estimate that lead-time-related phasing issues have contributed £104m to the apparent difference between spend and allowance in 2023/24.
The 2023/24 asset health related plan, which is our work to replace or refurbish existing equipment on the transmission network, shows a forecast spend of direct capex £1.9bn over the RIIO-T2 period, which is £81m more than adjusted allowances of £1.8bn. The allowance adjustments reflect reductions for work not now forecast to be completed, balanced with additional allowances agreed through re-openers.
The net £81m overspend has been predominantly driven by:
The above overspends are offset by underspends on our RIIO-T2 mechanistic PCD categories, specifically Protection & Control and Overhead Line Conductor. For the Asset Health portfolio, we have also assessed the differences between spend and allowance. Based on splitting the differences in cost and allowance by the column headings in the table below, the £81m forecast overspend vs allowances has been allocated in the following manner:
In 2023/24, direct capex expenditure on the Asset Health Related portfolio was £326m which is £104m less than adjusted allowances of £430m. This difference between spend and allowance is predominantly driven by the following:
Non-operational Capex 5-year and 2023/24 view.
Our Non-Operational capex is spend on IT, Property and Fleet. The expectation was that total Non-Operational Capex in the RIIO-T2 period will be £74m less than total allowances of £393m (including re-opener allowances).
IT investment for the SCADA programme (how our network control systems are being replaced) forms the majority of this reported underspend. At the time of table population, however, a re-baselining of the SCADA programme was underway to capture an updated delivery profile; updating for these changes increases the forecast RIIO-T2 period spend to £372m which is £21m lower than the post-reopener allowances.
Our Non-Operational capex spend on IT, Property and Fleet in 2023/24 was £74m which is £21m lower than adjusted allowances of £95m. This reflects lower IT expenditure, which has largely been driven by re-phasing into future years. The remaining variance is made up of Property investment being lower than allowances, offset by higher vehicle purchases and EV charging investment. Network Operating Costs (NOC) are the total spend on faults, inspections, repairs and maintenance, vegetation management and legal and safety. It is forecast to be £737m, which is £81m higher than the adjusted allowance position of £656m for the RIIO-T2 period. The main drivers for this difference between spend and allowance is £46m overspend on legal and safety (predominantly flood defence work) and a £44m overspend on own-use electricity at substations.
In 2023/24, the total spend was £147m which was £15m more than allowances; this is mainly due to an increase in own-use electricity costs at substations (£7.6m) along with an overspend of £11.4m within the 'Repairs’ category, mainly due to a single major repair. This overspend is partially offset by an underspend on Inspections.
For the visual amenity projects (also included in NOC), our forecast is to spend £313m during RIIO-T2, a £6m underspend compared to adjusted allowances of £319m. This underspend is driven by a re-profiling of spend within the Eryri (Snowdonia) project; actual spend is not aligned with the assumed profile at the time of determination as delays were experienced in the launch shaft design which moved the Tunnel Boring Machine launch date back to April 2025.
Network Operating and Indirect Costs 5-year and 2023/24 view.
Network Operating Costs (NOC) are the total spend on faults, inspections, repairs and maintenance, vegetation management and legal and safety. It is forecast to be £737m, which is £81m higher than the adjusted allowance position of £656m for the RIIO-T2 period. The main drivers for this difference between spend and allowance is £46m overspend on legal and safety (predominantly flood defence work) and a £44m overspend on own-use electricity at substations.
In 2023/24, the total spend was £147m which was £15m more than allowances; this is mainly due to an increase in own-use electricity costs at substations (£7.6m) along with an overspend of £11.4m within the 'Repairs’ category, mainly due to a single major repair. This overspend is partially offset by an underspend on Inspections.
For the visual amenity projects (also included in NOC), our forecast is to spend £313m during RIIO-T2, a £6m underspend compared to adjusted allowances of £319m. This underspend is driven by a re-profiling of spend within the Eryri (Snowdonia) project; actual spend is not aligned with the assumed profile at the time of determination as delays were experienced in the launch shaft design which moved the Tunnel Boring Machine launch date back to April 2025.
Return on regulated equity (RoRE)
The Return on Regulatory Equity (RoRE) figure is a key measure by which Ofgem compares operational and financing performance across Network Operators. This encompasses the costs and allowances associated with a regulated business, including totex, financing, tax, incentive performance and company-funded innovation costs. A key concept in the RoRE calculation is enduring value.
RoRE aims to show the full value earned by the regulated company during the price control period. This is based on the enduring value, being the true value of the regulated business over the course of the price control. The enduring value of the business factors in the financial impact of any decisions or future events which have yet to be reflected in Revenue and RAV but are known at the time of estimation. Where possible forecasting is utilised to give a view of the true value of the regulated business, however, it does not accommodate all required adjustments. Therefore, several adjustments have been applied since the completion of last year’s report. These adjustments rephase allowances in line with spend to ensure performance is recognised when outputs are delivered. The enduring value adjustments impact on the network’s return and RAV and ultimately RoRE. Please note that the biggest factor in the in-year RoRE value is the large decrease in financing, from 6.2% last year to 3.9% this year, due to the reduction of inflationary pressures.
RoRE for 2023/24 and the RIIO-T2 period comprise the following components:
The Electricity Transmission part of your bill, which is subject to approval by the energy regulator, Ofgem, covers the cost of building and maintaining the network. Our transmission network cost in 2023/2024 was £24.50 of the average annual household bill.