The way we generate electricity in the UK is changing rapidly, and we are transitioning to cheaper, cleaner and more secure forms of renewable energy such as new offshore windfarms.
We need to make changes to the network of overhead lines, pylons, cables and other infrastructure that transports electricity around the country, so that everyone has access to clean electricity from these new renewable sources. These changes include a need to increase the capability of the electricity transmission system between the North and the Midlands, and between the Midlands and the South. It is also needed to facilitate the connection of proposed new offshore wind, and subsea connections between England and Scotland, and between the UK and other countries across the North Sea.
Our Grimsby to Walpole proposals are part of The Great Grid Upgrade.
Our first stage of our public consultation aimed to introduce you to National Grid Electricity Transmission (NGET), explain why an upgraded grid requires work in this area and outline our early proposals for a new electricity transmission line between a new substation at Grimsby and Walpole, along with three further new substations along the route.
We are proposing to build a new high-voltage electricity transmission line and associated works between a new substation at Grimsby West in North East Lincolnshire and a new substation in the Walpole area, in Norfolk. We are also proposing two new connection substations near the Lincolnshire coast and a new substation at Weston Marsh in Lincolnshire.
During our first stage of public consultation, we are sought views on:
We are committed to listening to your views and will consider these alongside planning policy, technical assessments and environmental surveys as we develop more detailed proposals. Your feedback provided during our first public consultation will help inform our more detailed proposals, which we will be presenting and consulting on during a further consultation in 2025. Feedback will be carefully considered as we further shape our proposals and we will report on that when we make an application to the Secretary of State for permission to build, operate and maintain the new assets.
For further details on our approach to our first public consultation, please see our Consultation Strategy. All documents published as part of this consultation, including the Project Background Document and related technical documents, can be found below.
We want to ensure that all stakeholders and communities are engaged in the development of our proposals and have the opportunity to comment on the proposals at key decision-making points. From 18 January 2024 to 13 March 2024, we held our first stage of public consultation to:
Our proposals will support The Great Grid Upgrade transition, the largest overhaul of the grid in generations make sure the grid is ready.
The energy industry plays a key part in this transition, from developing renewable energy generation technology to upgrading the existing transmission network to allow communities across the country to benefit from this clean energy.
Decarbonising the energy system and delivering cheaper and more secure energy supplies is one of the biggest challenges facing our world.
The UK is in the middle of a transformation, with the energy we use increasingly coming from cleaner, greener sources. In 2019, for the first time since the industrial revolution, most of our electricity came from low carbon sources. NGET is at the heart of that energy transformation – investing around £1.3 billion each year to adapt and develop our transmission network to connect new sources of low carbon and green energy to our homes and businesses.
NGET and the Government recognise that it is also important to keep the impact of the energy transition as low as possible on bills, people, communities and our natural environment. National Grid is committed to finding the right balance between these factors to ensure our projects have a sustainable, positive impact.
The UK already has 14.7 gigawatts (GW) of offshore wind energy in operation. The Government’s recent British Energy Security Strategy outlines the ambition to increase energy from offshore wind to 50 GW by 2030 – more than enough to power every home in the UK. In Powering Up Britain, the Government explains that the grid needs to be expanded at an unprecedented scale and pace to deliver more clean power and increase our energy security.
Delivering the infrastructure needed to achieve this ambition will boost local economies, provide jobs and opportunities to learn new skills, and bring vital investment to communities right across the country.
Grimsby to Walpole will support the UK’s net zero target by reinforcing the electricity transmission network in Lincolnshire, Cambridgeshire and Norfolk, and facilitate the connection of planned offshore wind generation, battery storage/solar, interconnectors with other countries and subsea links to Scotland, allowing clean green energy to be carried on the network.
The reinforcement is needed because our existing power lines do not have sufficient capacity for all the new sources of electricity that we expect to connect to the network over the next 10 years and beyond.
Our proposals include building a new 400,000 volt (400 kV) overhead electricity transmission line, new 400 kV substations at Grimsby West and Walpole, together with three new connection substations in Lincolnshire for planned new offshore wind generation, battery storage/solar, interconnectors with other countries and subsea links to Scotland.
Details of all our public information events and where you could to find more information during our first stage of public consultation can be found below.
You can sign up to receive project updates directly to your inbox by contacting the Community Relations Team by emailing [email protected] or calling 0800 0129 153.
Document | Description |
Providing a summary of our proposals and information on how to get involved. | |
Consultation newsletter | Summarising details of the Project and public consultation. |
Stage one feedback form | To gather comments and feedback from the public consultation. |
Consultation event banners | Banners used during public information events presented during the first stage of public consultation |
Consultation Strategy | Setting out the approach to the first stage of consultation. |
Explaining the strategic options considered to deliver the necessary network upgrade. | |
Explaining the work undertaken to consider the increased demand for connections to the network since the May 2023 Strategic Options Report. | |
Explaining the options considered for where the new Walpole substation could be located. | |
Providing more technical information on the project and the need for the project, the options considered, the routeing and siting options assessed and our preferred options. | |
Appendix A to the Corridor Preliminary Routeing and Siting Study | |
CPRSS Appendix B | Appendix B to the Corridor Preliminary Routeing and Substation Report |
Throughout the consultation, we held a series of face-to-face events. Our public information events were held across the local area. Information about our proposals was displayed and copies of maps and technical documents were made available to view. Members of the project team were available to talk through our proposals and answer any questions.
Event location | Date | Time |
Tydd St Giles Community Centre, Broad Drove East, Wisbech, Cambridgeshire, PE13 5LN | Wednesday 31 January 2024 | 2pm – 7pm |
Moulton Seas End Village Hall, Seas End Road, Moulton Seas End, PE12 6LD | Friday 2 February 2024 | 2pm – 7pm |
Burgh Le Marsh Village Hall, Springfield Jacksons Lane, Burgh Le Marsh, Irby In The Marsh, PE24 5LA | Wednesday 7 February 2024 | 2pm – 7pm |
Alford Corn Exchange, 9 Market Place, Alford, LN13 9EB | Saturday 10 February 2024 | 11am – 5pm |
North Thoresby Village Hall, The Square, North Thoresby, Grimsby. DN36 5QL | Tuesday 13 February 2024 | 2pm – 7pm |
Eastville, Midville, New Leake Village Hall, Station Road, New Leake, Lincolnshire, PE22 8LS | Friday 16 February 2024 | 2pm - 7pm |
Walpole Community Centre, Summer Close, Walpole St Andrew, Wisbech, PE14 7JW | Tuesday 20 February 2024 | 2pm - 7pm |
The Pavilion, London Road, Louth, LN11 9QP | Thursday 22 February 2024 | 2pm - 7pm |
Oaklands Hall Hotel, Barton Street, Laceby, Grimsby, Lincolnshire, DN37 7LF | Saturday 24 February 2024 | 11am - 5pm |
Hubberts Bridge Community Centre, Langrick Road, Hubberts Bridge, PE20 1SG | Tuesday 27 February 2024 | 2pm – 7pm |
Alvingham Village Hall, Yarburgh Road, Alvingham, Lincolnshire, LN11 0QG | Thursday 29 February 2024 | 2pm – 7pm |
We invited you to attend our online webinar sessions, where we presented details of our proposals followed by an open question and answer session. We held a series of general overview and location-themed webinars.
Webinar session | Date | Time |
Introduction to Grimsby to Walpole project proposals – general overview | Tuesday 23 January 2024 | 2pm |
Our proposals in Sections 1 (Grimsby West to Barnoldby le Beck) and 2 (Barnoldby le Beck to North Thoresby) | Thursday 25 January 2024 | 10am |
Monday 29 January 2024 | 7pm | |
Our proposals in Sections 5 Tothill to Cumberworth) and 6 (Cumberworth to Burgh le Marsh) | Monday 5 February 2024 | 2pm |
Thursday 15 February 2024 | 10am | |
Our proposals in Sections 7 Burgh le Marsh to Midville) and 8 (Midville to River Witham) | Saturday 2 March 2024 | 10am |
Tuesday 5 March 2024 | 7pm | |
Introduction to Grimsby to Walpole project proposals – general overview | Thursday 7 March 2024 | 2pm |
Paper copies of the consultation newsletter, Project Background Document and Feedback Form were made available to collect from one of the following local information points. These are located within or in close proximity to the emerging preferred corridor and documents could be collected from the start of and throughout the consultation period.
Reference copies of the Strategic Options Report, the Addendum to the Strategic Options Report, Corridor Preliminary Routeing and Siting Study and Project Background Document were also made available in these locations.
Local information point opening hours can be subject to change. Please check with the relevant venue for the most up-to-date opening hours.
Public information point | Opening times |
Grimsby Central Library | Monday – Closed |
Waltham Library | Monday – Closed |
Louth Library | Monday, Wednesday and Friday – 9am–5pm |
Alford Library and Focal Point | Monday, Wednesday and Thursday – Closed |
Burgh Le Marsh Library Hub Tinkers Green, Jacksons Lane, Burgh le Marsh, Skegness PE24 5LA | Monday, Wednesday and Friday – Closed |
Skegness Library | Monday–Wednesday and Friday – 9am–5pm |
Boston Library | Monday – Friday, 9am–5pm |
Spalding Library | Monday – Wednesday and Friday – 9am–5pm |
Holbeach Community Library | Monday and Thursday – 1pm–4pm |
Long Sutton Library | Monday and Thursday – 2pm–6pm |
Wisbech Library | Monday – 9.30am–1pm |
View a webinar which provides a general overview of the Grimsby to Walpole project.
Watch the videoVirtual exhibition room
You can find out more information about our proposals for Grimsby to Walpole, as presented during our first public consultation, in our virtual exhibition room. Click here to enter.