On this page you can find all the materials we have produced for current and historic consultations on North Humber to High Marnham, including the information published as part of our ongoing statutory consultation. These documents will also be available to view in-person at our public information events and at local information points across the project area - for more information see our Have your say page (linked above).

2025 statutory consultation documents

In this section you can view the key documents published as part of our statutory consultation. We encourage you to provide feedback after reading our Project background document, which outlines our proposals and early environmental studies. More detailed information, including preliminary environmental information, can be found using the menu at the side of the page.

A printable copy of the Feedback questionnaire is available to download from this page. You can also submit your feedback online.
 

Project background document
Feedback questionnaire
Community newsletter
Non-technical summary of the Preliminary environmental information report
Non-technical summary of the Preliminary environmental information report - Figures
Consultation banners
Strategic options report update
Design development report
Statement of community consultation
Non-statutory consultation feedback report
Section 47 notice
Section 48 notice

2025 statutory consultation plans

In this section you can view detailed PDF plans of our proposals. You can also view the proposals on our Interactive map.

Guide to interacting with our consultation plans
Overall location plan
Master key plan
Route section 1: Creyke Beck-Skidby
Key plan
Consultation plan series
Route section 2: Skidby–A63 dual carriageway
Key plan
Consultation plan series
Route section 3: A63 dual carriageway–River Ouse crossing
Key plan
Consultation plan series
Route section 4: River Ouse crossing
Key plan
Consultation plan series
Route section 5: River Ouse crossing–Luddington
Key plan
Consultation plan series
Route section 6: Luddington–M180 motorway
Key plan
Consultation plan series
Route section 7: M180 motorway–Graizelound
Key plan
Consultation plan series
Route section 8: Graizelound–Chesterfield Canal
Key plan
Consultation plan series
Route section 9: Chesterfield Canal–A620 east of North Wheatley
Key plan
Consultation plan series
Route section 10: A620 east of North Wheatley–Fledborough
Key plan
Consultation plan series
Route section 11: Fledborough–High Marnham
Key plan
Consultation plan series

2025 statutory consultation Preliminary environmental information report

In this section you can view our Preliminary environmental information report (PEIR), which considers the likely significant effects of our proposals on the environmental, along with the measures we are proposing to avoid, reduce or mitigate these impacts. The PEIR has been split into several chapters, along with figures and appendices. You can also read a shorter Non-technical summary of the PEIR.

Chapter 1 - Introduction
Volume 1 Chapter 1 Introduction
Volume 2 Chapter 1 Figures
Chapter 2 – Legislation and planning policy context
Volume 1 Chapter 2 Legislation and planning policy context
Chapter 3 – Project need and alternatives
Volume 1 Chapter 3 Project need and alternatives
Chapter 4 – Description of the project
Volume 1 Chapter 4 Description of the project
Volume 2 Chapter 4 Figures
Volume 3 Appendix 4.1 Outline Code of Construction Practice
Volume 3 Appendix 4.2 Indicative Pylon Schedules
Volume 3 Appendix 4.3 Indicative Bridge and Culvert Schedule
Chapter 5 – Approach to preparing the PEIR
Volume 1 Chapter 5 Approach to preparing the PEIR
Chapter 6 – Landscape
Volume 1 Chapter 6 Landscape
Volume 2 Chapter 6 Figures
Volume 3 Appendix 6.1 Landscape Assessment Methodology
Volume 3 Appendix 6.2 Landscape Baseline
Chapter 7 – Visual
Volume 1 Chapter 7 Visual
Volume 2 Chapter 7 Figures
Volume 3 Appendix 7.1 Visual Assessment Methodology
Volume 3 Appendix 7.2 Proposed Viewpoints
Chapter 8 – Ecology
Volume 1 Chapter 8 Ecology
Volume 2 Chapter 8 Figures
Volume 3 Appendix 8.1 Designated Sites
Volume 3 Appendix 8.2 HRA Preliminary Stage 1 Report
Chapter 9 – Ornithology
Volume 1 Chapter 9 Ornithology
Volume 2 Chapter 9 Figures
Volume 3 Appendix 9.1 Ornithology Baseline Report
Volume 3 Appendix 9.2 Preliminary Assessment Tables
Chapter 10 – Cultural heritage
Volume 1 Chapter 10 Cultural heritage
Volume 2 Chapter 10 Figures
Volume 3 Appendix 10.1 Gazetteers of Cultural Heritage Assets
Chapter 11 – Water environment
Volume 1 Chapter 11 Water environment
Volume 2 Chapter 11 Figures
Volume 3 Appendix 11.1 Water Environment Baseline
Chapter 12 – Geology and hydrogeology
Volume 1 Chapter 12 Geology and hydrogeology
Volume 2 Chapter 12 Figures
Volume 3 Appendix 12.2 Preliminary Qualitative Mineral Resource Assessment 
Chapter 13 – Agriculture and soils
Volume 1 Chapter 13 Agriculture and soils
Volume 2 Chapter 13 Figures
Chapter 14 – Traffic and transport
Volume 1 Chapter 14 Traffic and transport
Volume 2 Chapter 14 Figures
Volume 3 Appendix 14.1 Traffic and Transport Baseline Conditions
Volume 3 Appendix 14.2 Future Baseline
Volume 3 Appendix 14.3 Preliminary Construction Effects
Chapter 15 – Air quality
Volume 1 Chapter 15 Air quality
Volume 2 Chapter 15 Figures
Volume 3 Appendix 15.1 Construction Dust Methodology and Assessment
Chapter 16 – Noise and vibration
Volume 1 Chapter 16 Noise and vibration
Volume 2 Chapter 16 Figures
Volume 3 Appendix 16.1 Construction Noise and Vibration Data
Volume 3 Appendix 16.2 Construction Traffic Noise and Vibration Assessment
Chapter 17 – Socio-economics, recreation and tourism
Volume 1 Chapter 17 Socio-economics, recreation and tourism
Volume 2 Chapter 17 Figures
Chapter 18 – Health and wellbeing
Volume 1 Chapter 18 Health and wellbeing
Volume 2 Chapter 18 Figures
Chapter 19 – Climate change
Volume 1 Chapter 19 Climate change
Volume 3 Appendix 19.1 Climate Change Risk Assessment
Volume 3 Appendix 19.2 In Combination Climate Impact Assessment
Chapter 20 – Substations and associated works
Volume 1 Chapter 20 Substations and associated works
Chapter 21 – Cumulative effects
Volume 1 Chapter 21 Cumulative effects
Volume 2 Chapter 21 Figures
Volume 3 Appendix 21.1 Long List of Other Developments
Volume 3 Appendix 21.2 Stage 1 and 2 Preliminary Cumulative Assessment
Volume 4 – Photomontages
Volume 4 Photomontages

2025 statutory consultation construction animations

In this section you can watch animations that provide an indicative overview of how National Grid builds new infrastructure.

Bellmouth construction
Haul road construction
Pylon/tower construction
Conductor/wire stringing
Reinstatement