Following the successful delivery of our Tunnel Boring Machine (TBM), the Eryri VIP project team is continuing with its preparation for the start of construction of the new tunnel under the Dwyryd Estuary.
To ensure that the project remains on schedule, a small team will be continuing to work on the construction of the TBM’s launch shaft at our site in Garth, near Minffordd on some days over the Christmas and New Year period.
This activity will be taking place on the following days:
All construction work on our site at Llandecwyn will be paused over the festive period, resuming on Monday 6 January.
Hochtief UK’s accommodation facility in Blaen Cefn will also be fully closed during this two-week period, although 24hr security staff will remain on site.
We appreciate the ongoing patience and cooperation of the local community as we carry out these works and will continue to minimise any disturbance caused to our neighbours.
If you have any questions about this or any matter relating to the project, please contact the Eryri VIP project team by emailing us at [email protected] or calling 0800 018 1898. If we are unable to answer your call immediately, please leave a message and a member of our team will get back to you.
On behalf of the entire team working on the Eryri VIP scheme, we would like to wish you a peaceful Christmas and a Happy New Year.