Commissioning of Tirley to Three Cocks (Feeder 28) Pipeline

National Grid hereby notifies users of its intention to commence filling the new 90 km Tirley to Three Cocks (feeder 28) pipeline with gas.

Work is scheduled to start wc 12th November and will be carried out over a 3-4 day period to minimise any effect on the wholesale markets. As a consequence of the requirement for ~ 7MCM of gas supplies to be delivered and retained within the expanded System, Users may see a steady increase to the daily opening linepack levels.

This is the second phase (of a three phase process) to link two LNG importation terminals at Milford Haven with the existing NTS Pipeline system.