faqs
What are the timescales for the CUSC Modification Process and who is responsible for establishing them?
Timescales for each phase of the Modification process are set out in the CUSC. The timetable for consideration by a Workgroup (if any) is established by the Modifications Panel, but shall be no longer than three months. The timetable for the wider consultation and separately the preparation of the Modification Report is established by National Grid, but shall be no longer than two months for the consultation and another fourteen days for preparation of the Modification Report. These timescales may not be extended unless a particular Modification Proposal justifies such an extension and provided the Authority does not object.