Current and future developments

In addition to the current and future developments described here, the following developments are relevant to the Gas Distribution business.

Rhode Island gas rate plan filing

We filed a request on 1 April 2008 with the Rhode Island Public Utilities Commission for a $20.4 million (£14.2 million) rate increase, representing a 4.6% increase on a total bill basis. In November, we were granted a $13.6 million (£9.4 million) rate increase with a 10.5% return on equity, effective as of 1 December 2008. The case has a discrete funding mechanism for a mains replacement programme, a new rate for low income customers, and an increased recovery of commodity related bad debt expense. Our decoupling proposal was rejected and the Commission indicated that full revenue decoupling was not appropriate at this time.

Upstate New York gas rate plan filing

We filed a rate plan with the New York Public Service Commission on 23 May 2008 for an $84 million (£58 million) rate increase in natural gas delivery rates. We filed a settlement proposal on 13 February 2009, which included a two year rate plan, a $39.4 million (£27.4 million) rate increase in year one resulting in an overall 5.1% increase on customer bills. The settlement contains a 10.2% return on equity, revenue decoupling, a new rate for low income customers, a partial recovery of commodity related bad debt expense based on current gas costs, a full recovery of New York State Energy Research and Development Authority (NYSERDA) auction rate debt, and a partial recovery of new long-term debt. The Commission will rule on the settlement during 2009, with new rates expected to come into effect during the year.

New Hampshire gas rate plan filing

On 25 February 2008, we filed a request with the New Hampshire Public Utilities Commission to increase distribution rates by approximately $9.9 million (£6.9 million). The filing marks the first request for an increase in distribution rates in 15 years and is necessary to fund ongoing operations and significant infrastructure improvements. On 23 January 2009, we filed a partial settlement addressing all issues other than the return on equity. The return on equity was fully litigated. The partial settlement includes a commodity related bad debt allowance in the first year of 2.54%, (decreasing to 1.75% in year four) increased customer charges, an enhanced collections programme and the elimination of the requirement to connect new customers to the system at no charge who are within 80 feet of the network. The Commission ruling is expected in 2009 and will cover the settlement and the return on equity.