Modernising and extending our networks
Reliability
In addition to meeting reliability performance targets agreed with our regulators, our objective is to improve reliability.
To monitor our reliability performance we use industry average outage frequency and duration as our key performance indicator.
The system average interruption duration (SAIDI) for 2008/09, being the time the average customer is without power during the year, was 114 minutes, compared with a target of below 120 minutes and 110 minutes in 2007/08.
Our customers depend on a reliable electricity distribution service. In 2008, we achieved our regulatory targets for our Rhode Island, Massachusetts and upstate New York electricity operations, while Long Island operations continued to achieve first quartile reliability performance based on 2007 data. Although we did not meet the LIPA management service agreement metric for average customer interruption duration, no monetary penalties were incurred as strong performances against other operational metrics provided an offset.
In 2009, we intend to meet internal targets that move towards achieving first quartile reliability performance by 2013. A key element to delivering these targets and achieving sustainable improvements in reliability will be the continued investment in our distribution infrastructure.
As we enter the fourth year of the five year reliability enhancement programme, we are now realising the benefits. We will continue to replace ageing underground cables, overhead lines, protection/control systems and substation infrastructure as part of our asset replacement programme, and continue our ongoing reliability enhancement programme. This programme also includes:
- feeder hardening – upgrading our worst performing overhead electricity circuits by replacing aged and deteriorated components and protecting against lightning strikes and animal contacts; and
- inspection and maintenance – increasing our preventative maintenance and repair activities to find potential faults before they occur to improve reliability and public safety.
We will also continue our vegetation management programme across all operating areas, increasing our focus on dealing with hazardous trees.
We plan to invest over $520 million in our networks across New England and New York during 2009/10, delivering on our commitment to invest $1.47 billion in upstate New York over four years. In addition, with the asset replacement programme agreed with LIPA, we will be investing an estimated $237 million in the LIPA distribution and transmission infrastructure.
Overall, we propose to invest over $750 million in the renewal of our infrastructure during 2009/10.
Capital investment
Our objective is to deliver our capital investment plans over the next five years.
Capital investment in the replacement, reinforcement and extension of our US electricity distribution networks was £355 million in 2008/09, £257 million in 2007/08, and £218 million in 2006/07. After excluding the effect of exchange movements of £79 million in 2008/09 compared with 2007/08, capital investment increased by £19 million. This reflects a £10 million increase from a full year of generation capital expenditure compared with a partial year in 2007/08 following the KeySpan acquisition, higher investment at the Port Jefferson and Northport generating stations of £7 million, increased capital related storm costs of £6 million, and other investment including asset replacement of £23 million. This higher expenditure has been partially offset by decreased capital lease additions of £15 million relating to vehicles and lower investment in new business installations of £12 million as a result of the downturn in the US economy.
After excluding the effect of exchange movements of £11 million in 2007/08 compared with 2006/07, capital investment increased by £50 million. This reflected an increase of £17 million in spend related to our reliability enhancement programme, recognition of finance leases related to vehicles of £18 million, other increases in capital investment of £11 million and £13 million of capital investment in the operations acquired with KeySpan, partially offset by a non-recurring benefit capitalisation adjustment made in 2006/07 of £9 million.